1Z0-1129 PDF, 1Z0-1129 Dumps PDF Free Download, 1Z0-1129 Latest Dumps Free PDF, Primavera P6 Enterprise Project Portfolio Management Professional PDF DumpsThe Oracle Primavera P6 Enterprise Project Portfolio Management Professional (1Z0-1129) Sample Question Set is designed to help you prepare for the Oracle Primavera P6 Enterprise Project Portfolio Management Certified Professional certification exam. To become familiar with the actual Oracle Certification exam environment, we suggest you try our Sample Oracle 1Z0-1129 Certification Practice Exam.

This Oracle Primavera P6 Enterprise Project Portfolio Management Professional certification sample practice test and sample question set are designed for evaluation purposes only. If you want to test your Oracle 1Z0-1129 knowledge to identify your areas of improvement and get familiar with the actual exam format, we suggest you prepare with the Premium Oracle Primavera P6 Enterprise Project Portfolio Management Certified Professional Certification Practice Exam. Our team of Oracle Construction and Engineering experts has designed Questions-Answers for this premium practice exam by collecting inputs from recently certified candidates. Our premium Oracle 1Z0-1129 certification practice exam will boost your confidence as well as your actual Oracle Primavera P6 Enterprise Project Portfolio Management Professional exam result.

Oracle 1Z0-1129 Sample Questions:

01. How can project stakeholders benefit from the dashboard functionality in Primavera P6?
(Choose two)
a) Access filtered metrics through configurable portlets
b) Automate role assignments using dashboard data
c) View summary data across all active projects
d) Adjust global calendars based on portlet input
 
02. When creating tasks under a WBS in Primavera P6, which of the following features are available?
(Choose two)
a) Assigning roles and resources to tasks directly
b) Using WBS filters to display selected task groups
c) Creating resource profiles specific to the WBS
d) Viewing task hierarchy in outline or tree format
 
03. In Primavera P6, activities linked between different projects use __________ relationships to reflect their scheduling dependencies.
a) Inter-WBS
b) Cross-resource
c) External
d) Baseline
 
04. When should a project manager use the “Schedule All Open Projects” option in Primavera P6?
a) When needing to perform risk analysis
b) When activities across projects are logically linked
c) When exporting portfolio data to external systems
d) When resetting OBS user access at the program level
 
05. Why is selecting the correct duration type important in Primavera P6 resource planning?
a) It ensures that activity codes are auto-assigned
b) It links baseline start and finish to actuals automatically
c) It determines how changes to resource units or duration affect each other
d) It guarantees project-wide float optimization
 
06. What does the “Schedule Check Report” help project managers identify in Primavera P6?
a) Activity progress against baseline
b) Data issues that may impact schedule integrity
c) Resource leveling priorities
d) Portfolio alignment mismatches
 
07. You want to analyze risks associated with specific activities. Which two actions can be taken directly in Primavera P6?
(Choose two)
a) Link risks to activities on the Activities page
b) Assign risk categories to WBS codes
c) View thresholds applied to activity-level risks
d) Convert risk types into custom activity calendars
 
08. A project manager changes the resource units on a fixed duration task. What happens if the duration type is set to "Fixed Duration and Units"?
a) Duration is reduced to match effort
b) Units/Time increases to maintain duration
c) New baseline values are automatically created
d) Float is reset for that activity
 
09. You’re tasked with ensuring that resource leveling does not delay project completion. Which two actions would help ensure this in Primavera P6?
(Choose two)
a) Apply “Preserve Scheduled Early and Late Dates” option
b) Level only selected activities with high priority
c) Disable leveling for critical activities
d) Restrict leveling to within total float
 
10. Which of the following actions can be performed on the Activities page in Primavera P6 EPPM?
(Choose two)
a) Change system-wide calendar settings
b) View activity Gantt charts
c) Assign resources directly to an activity
d) Modify project-level codes and dictionaries

Answers:

Question: 01

Answer: a, c

Question: 02

Answer: b, d

Question: 03

Answer: c

Question: 04

Answer: b

Question: 05

Answer: c

Question: 06

Answer: b

Question: 07

Answer: a, c

Question: 08

Answer: b

Question: 09

Answer: a, d

Question: 10

Answer: b, c

 