01. Projects A and B are tied by an external relationship: an activity in A drives one in B. A scheduler opens and schedules Project B alone, without Project A open.
What is the risk to Project B's dates?
a) Project B cannot be scheduled at all unless Project A is first deleted
b) The external relationship is ignored permanently once it has been set once
c) Project A's own dates will be overwritten by Project B's calculation run
d) Project B may calculate against a stale external date carried over from Project A
02. A team debates whether to record exposures qualitatively as High/Medium/Low or to insist on fully quantified cost-and-time distributions for every risk at the outset.
What best justifies a qualitative matrix early on?
a) A matrix ranks exposures quickly with limited data, reserving quantification for the few
b) A matrix removes the need to reassess any of the risks as the project proceeds
c) Qualitative ratings are simply more accurate than any quantified estimate would be
d) Quantified risk analysis is never useful on construction and engineering projects
03. On the team usage view a key resource peaks above its availability line in weeks 3 and 7, with clear troughs in weeks 4 to 6. The project finish is flexible and the peaked activities carry float.
What is the most appropriate first optimization?
a) Remove the resource from the peaked activities so the histogram flattens out
b) Shift the floated peak work into the trough weeks to smooth demand within float
c) Set a Mandatory Start on the peaked activities so they are held firmly in place
d) Hire extra resources immediately so that both of the demand peaks are covered
04. A project is behind and must be recovered. The scheduler weighs overlapping two sequential activities against adding resources to shorten a critical activity.
Which statement best distinguishes the two recovery techniques?
a) Both techniques shorten the project with no added cost and no added schedule risk
b) Adding resources never shortens a critical activity, so only overlapping recovers time
c) Overlapping adds risk from parallel work, while adding resources raises cost to compress
d) Overlapping always reduces risk, because the parallel work simply finishes sooner
05. Midway through execution an approved scope change significantly alters the remaining plan. A scheduler debates whether to keep comparing to the original baseline or to capture a new approved one.
What is the soundest practice?
a) Capture a new approved baseline for control and keep the original for history
b) Delete every baseline, because variance is meaningless after a scope change
c) Overwrite the original baseline so that the variance reports stay simple
d) Keep only the original baseline and never re-baseline during the execution
06. A company-wide holiday is set non-working on the global calendar. One resource's individual calendar does not mark that date non-working, and the resource is on a Resource Dependent activity.
Which calendar governs whether the resource can work that date?
a) The resource's own calendar, so the resource may work despite the global holiday
b) Whichever calendar holds fewer total working hours across the year
c) The global calendar, so the resource is prevented from working that date
d) The project calendar, which always supersedes both of the other two
07. Testing can begin only after installation finishes, and both activities should also complete together so a joint sign-off can occur. Which combination of relationships models this most faithfully?
a) A single Start-to-Finish relationship linking installation into testing
b) A single Start-to-Start relationship carrying a positive lag between them
c) A single Finish-to-Start relationship linking installation into testing
d) A Finish-to-Start tie for the start plus a Finish-to-Finish tie for the finish
08. As the data date advances and progress is recorded, a scheduler sees the baseline bars staying fixed in the Gantt while the current bars move. What does this behavior correctly represent?
a) Both sets of bars should move together whenever the schedule is healthy
b) The current bars are frozen while the baseline acts as the live schedule
c) The baseline is a frozen reference while the current schedule evolves with progress
d) The baseline bars are failing to refresh, so they ought to be recaptured now
09. A PMO compares two projects: Project A shows a Finish Variance of -3 days against its baseline, Project B shows -20 days. An executive concludes Project B is simply worse-managed.
What qualification should the PMO add?
a) Finish variance can never be compared across different projects by any method
b) Each variance is relative to its own baseline and scale, so raw days do not compare
c) Project B is definitely worse, because a 20-day figure exceeds a 3-day figure
d) The negative signs mean both projects are comfortably ahead of their plans
10. A Resource Dependent activity has two resources working in parallel from the same start. Resource 1's calendar gives it 8 working days for its share; Resource 2's calendar gives it 11 working days.
When does the activity finish?
a) After 19 working days, the sum of the two resources' separate durations
b) After about 9.5 working days, the average of the two resource durations
c) After 11 working days, when the longer-running resource completes its share
d) After 8 working days, when the faster resource completes its own share